Austin voters approve a dedicated tax rate for Project Connect’s system plan.
Original system map ↗01 / How we got here
A big vision met
the reality of delivery.
The 2020 vote created a permanent funding stream for a broader transit program—not a legally frozen blueprint for one exact alignment. Inflation, design changes and technical constraints forced a smaller first rail phase.
Orange + Blue light rail, a downtown tunnel, and a direct airport connection anchor the original concept.
Light-rail cost estimates rise from $5.8B to $10.3B; scope must be reset.
Austin, CapMetro and ATP adopt the 9.8-mile surface-focused Phase 1.
FTA issues the Final EIS Record of Decision, completing federal environmental review.
Record of Decision ↗Construction is scheduled to begin, contingent on funding and final delivery decisions.
Phase 1 is planned to open for service.
Drag to compare
What voters saw vs. what Phase 1 is now
Two light-rail corridors, a downtown tunnel, and rail directly to the airport within a larger transit package.
- Longer north–south reach
- Downtown tunnel
- Airport connection
9.8 miles from 38th Street to Oltorf and Yellow Jacket, mostly at street level, with 15 stations.
- No downtown tunnel
- Airport is a future extension
- Designed to expand later
Important: Voters approved a tax rate and a citywide program described on the ballot. The exact 9.8-mile design was selected in 2023 after a public alternatives process. Read the 2020 ballot language ↗